Dampier Highway Duplication
Contract: C304/08

Client: Main Roads WA

Location: Karratha

Timeframe: January 2011 – December 2012

Project Value: $42M up to $80M (pending optional works) 

Project Description

The Dampier Highway Duplication design and construct project is being undertaken by the Highway Works Albem (HWA) Joint Venture in partnership with Main Roads WA.

The project has initially been awarded for the construction of 7km of new road between the Karratha townsite and airport. The optional works involve extending the road an additional 5km from the airport to the Burrup Road intersection.


The initial works package includes:

  • Duplicating the highway between Balmoral Road (Karratha townsite) and Bayly Avenue (airport turn off);
  • Linking 10 intersections into the new highway;
  • Construction of a new bridge at Seven Mile Creek;
  • Strengthening works and improvements to the existing bridge at Seven Mile Creek;
  • Construction of signalised intersections at the intersections with Madigan Road and the relocated Rubbish Tip Road;
  • Resurfacing of the existing Highway and connecting roads;
  • Improvements to pedestrian linkages; and
  • Construction of an on road cycling facility

The optional works include:
  • Duplicating the highway between Bayly Avenue (airport turn off) and Burrup Road (near Dampier);
  • Construction of a signalised intersection at the Burrup Road intersection with Dampier Highway
  • Construction across the salt flat causeway
  • Resurfacing of the existing Highway and connecting roads;
  • Improvements to pedestrian linkages; and
  • Construction of an on road cycling facility
Design works commenced in November 2010 with construction from April 2011 to December 2012.

Special Features/Challenges:
  • Construction of high strength concrete pavements at critical intersections
  • Construction of a second carriageway across a 3km salt flat causeway
  • Drilling and blasting at the Burrup including protection of heritage sites and the Dampier Bunbury pipeline
  • Installation of traffic signals

For more information, please visit the Dampier Highway project website by clicking here.

Project images
Burrup Road Intersection
Seven Mile Bridge
Dampier Highway Early Morning Traffic
Dampier Highway Salt Flats
Dampier Highway Rock Cutting