Great Northern Highway 1A Project Update, Jan 2010
21/01/2010 5:12:00 PM
Work is well underway on the upgrade to
the Great Northern Highway between Lennard Street and Haddrill Road.
The Services Authorities have relocated all water, power and
telecommunications services, which should mean an end to any major
service disruptions (see ‘Emergency Contacts’ list to find out who to
contact if you do experience problems).
Bus stops have been moved to their temporary locations during the
roadworks, with gravel bus bays being created to allow buses to pull off
to the side of the road to collect and drop off passengers.
Two lanes have been maintained throughout this phase of the work, and
this will continue to be a priority for contractor Highway Construction.
Temporary accesses have been created for properties along the Padbury
Road to Haddrill Road and McDonald Street to River Road stretch of the
Highway, where a temporary sealed road has been created to the East of
the existing road.
All land clearing has now been completed, with trees removed where
necessary.
The project is currently running on schedule, and contractors Highway
Construction are confident of works being completed by the middle of the
year.
What’s next?
During the coming weeks the new section of the road will begin to take
shape, with asphalting of the northern carriageway starting in late
January.
Once the asphalting is completed in mid-March, traffic will be
transferred across to this new section of road to enable work to begin
on the southbound lane.
Work will continue on this section until late May.
Streetlights will start to be installed from early April and will be
operational by the end of M
Comments and queries:
Highway Construction has appointed a Community Relations Manager (Louise
Richardson) to act as the contact point for road users and the local
community who have queries or concerns about the day to day management
of the road works.
Louise can be contacted on 0411 141 842 or via email at gnh@hicon.com.au
You can also Contact
Us through our website. Further information about the project can
be found here at our GNH
Section 1A Project Page.
On behalf of the construction workers and project team, we would like to
thank you in advance for your patience and safe driving during this
time.